| Sabiya EPP 300 MW ISO, Sabiya Emergency Power Project 2008 |
|
| Project |
EPC Contract for 300 MW ISO Gas Turbine Plant at Sabiya, Kuwait |
| Client |
Ministry of Energy (Electricity and Water) |
| Main Contractor |
Alghanim International |
| Alghanim Role |
Main EPC Contractor |
| Value |
USD. 308,000,000/- |
| Duration |
6 Months Construction + 5 Years O&M |
|
|
| Project Features: |
|
 |
6 x GE LM6000 Gas Turbine Generator Sets |
 |
3 x 120 MVA, 11/275 kV Generator Step Up Transformers – GE Prolec |
 |
2 x 5000 Tons Chillers for Turbine Inlet Cooling and Cooling Towers – TAS |
 |
3 x 2250 HP Fuel Gas Compressors – Valerus |
 |
275 kV Oil filled H.T. Cables – China Cables |
|
| |