| Az-Zour South Combined Cycle Conversion (560 MW) |
| Az-Zour South Combined Cycle Conversion Project |
|
| Project |
EPC Contract for 560 MW Conversion of Open Cycle Plant at
Az-Zour South, Kuwait to Combined Cycle |
| Client |
Ministry of Energy (Electricity and Water) |
| Main Contractor |
JV of Siemens A/G, AI and CMI |
| Alghanim Role |
Main EPC Contractor |
| Value |
USD. 728,189,000/- |
|
|
| Project Features: |
|
 |
2 x 280 MW Siemens SST-5000 Series Steam Turbines |
 |
Cooling Towers – 2 Trains of 32 x 110 x 30 m high Cooling Towers |
 |
1 x 700 MVA, 11/275 kV Generator Step Up Transformer – Siemens |
 |
Cooling Water pipes - 2.5 Km. of pipe of average diameter 2.2 Mts. |
|
| |
| View Photo Gallery |
|
 |
|